Helena Partnerships Bathroom Replacement

Helena Partnerships Bathroom Replacement2018-07-25T14:22:21+00:00

Project Description

Helena PartnershipsHelena Partnerships Bathroom Replacement Programme

Overview

Helena Bathrooms Phase 6, was the first contract Frank Rogers had undertaken for Helena Housing, and the first kitchen or bathroom contract with a value in excess of £1million, marking a significant milestone for the firm.

The contract was allocated via Fusion 21, and gave recognition for the firm’s success on previous smaller contracts successfully undertaken since 2003.

The contract consisted of 600 bathroom replacements, running at 15 installations per week. Completed within 40 weeks on time and within budget, Frank Rogers continue to carry out projects ranging in size and discipline today for the housing association

Frank Rogers achieved a Considerate Constructor accreditation – Performance beyond compliance.