Project Description

Project details:

Client: Bishop Martin CE Primary School, Liverpool
Project: Bishop Martin CE Primary School, Woolton – Flood Remedial Works
Programme: 4 weeks
Value: £45,000

Download Case Study (PDF)

Overview
Frank Rogers continue schoolwork across Merseyside supporting Bishop Martin Primary overcome significant flooding during term time.

Scope of Works
Our technical team completed a thorough investigation into probable flooding causes, identifying substandard parapet wall / rainwater outlet detail, resulting in standing water leaking through the building collapsing ceilings and damaging WC and classroom areas.
We replaced damaged roofing timbers, insulation and protective finishes improving rainwater outlets flushing drains. Internally, we replastered ceilings, redecorated and laid new vinyl flooring followed by a professional deep clean.

Programme
Our Contracts Manager devised a 2-week mobilisation programme mitigating further water ingress to the school. Working with facilities staff we considered school activities coordinating material deliveries between 10.00am – 2.00pm avoiding school drop-off and collection.

Health & Safety
We developed annotated drawings supporting our Safe Systems of Works and Programme, discussing with teachers improving their understanding for how works would progress around the school and what temporary restrictions, health and safety precautions would result.

Customer Satisfaction & Testimony
Our dedicated team worked tirelessly across Bishop Martin CE Primary School achieving completion within a tight 4 -week programme, on budget and to a high standard. Implementing safe systems of work together with regular informative information alleviated stress and disturbance to teachers and school children during the project.

Mr D Fendle, School Business Manager at Bishop Martin School

“Frank Rogers have recently completed a reinstatement of flood damage to our school. As you can imagine the complexities of resolving this level of work in a normal environment, Frank Rogers successfully delivered this project without issue and minimal disruption whilst the school was still fully open. They are an extremely responsible and professional contactor committed to ensuring customer satisfaction.